PRPA Announces Completion of Fairview-Ridley Connector Corridor Project


EFFECTIVE AUGUST 24, 2022

PRINCE RUPERT, BRITISH COLUMBIA – The Prince Rupert Port Authority’s (PRPA) Fairview-Ridley Connector Corridor formally opened today with an official ribbon cutting ceremony. Testing on the route got underway in mid-August, with container truck traffic beginning to travel to the newly opened southern gate at DP World-Prince Rupert Fairview Container Terminal, and the Corridor is set to be fully operational on August 29, 2022. The private haul road and two additional rail sidings now in place enable greater efficiency and competitive advantages at the Port of Prince Rupert, while improving public safety and supporting PRPA’s carbon reduction strategy.

The Connector Corridor was developed by PRPA as a critical component of the Prince Rupert Gateway’s intermodal ecosystem, a closed loop system of road and rail infrastructure that connects transloading and marine terminal operations within the Port’s existing footprint. The road and rail corridor directly links Fairview Terminal, both current and future capacity, with future import and export logistics sites on South Kaien Island and Ridley Island, that will offer new opportunities for Canadian businesses to reach global markets through containerized trade.

Stretching around the southwestern edge of Kaien Island, the Connector Corridor shortens the distance trucks must travel from existing transloading sites in Prince Rupert and future facilities to Fairview Container Terminal. By steering drivers away from urban areas and onto PRPA-owned roads, the Connector Corridor will help cut commercial vehicles emissions by up to 75 percent and reduce truck traffic congestion in the city of Prince Rupert.

“The Fairview-Ridley Connector Corridor is a key example of the Prince Rupert Port Authority’s proactive approach to land use planning and is designed to maximize efficiency within the Port complex, simultaneously upholding our commitment to reduce the impacts of Gateway operations on the environment and surrounding community,” said Shaun Stevenson, President & CEO of the Prince Rupert Port Authority. “With the addition of this infrastructure, we can enable greater efficiencies and competitiveness at the Prince Rupert Gateway and generate new economic opportunities on local, regional, and national levels.”

In addition to supporting trade and environmental targets, the Fairview-Ridley Connector Corridor has provided significant benefit to local and Indigenous workers, subcontractors, and other stakeholders, as well as enabled local and Indigenous skills training and employment in the surrounding community and Pacific Northwest region. The construction was undertaken by the Coast Tsimshian Northern Contractors Alliance (CTNCA), a local First Nations joint venture led by Prince Rupert Lax Kw’alaams Band and Metlakatla First Nation. Contracts awarded to CTNCA for the project, as well as the related habitat compensation work in Seal Cove, totaled more than $135 million, the most significant in PRPA’s history. Most of the construction was completed during the pandemic and at the project’s peak 118 people, working three rotating shifts, preserved to complete the extensive in-fill work.

“CTNCA was honoured to be the contractor of choice on the Fairview-Ridley Connector Corridor and had the pleasure of working collaboratively with the Prince Rupert Port Authority to construct the nearly five-kilometre road and we are encouraged by the relationship we have created together,” said Metlakatla First Nation Chief Harold Leighton. “When PRPA uses Coast Tsimshian owned businesses, like CTNCA, they are helping to provide true economic, employment, and training opportunities to local and Indigenous workers which directly and positively impacts the First Nation communities and their members. We are hopeful the positive relationship that was built between PRPA and CTNCA through this project will continue long-term and in a significant way on other Port of Prince Rupert projects.”

“The Fairview-Ridley Connector Corridor is an example of a creative solution that has a positive social, environmental, and economic impact, particularly at a time when trucking and logistics industries face challenges across North America. It also uniquely positions the Port of Prince Rupert to serve supply chains in the future, by developing an intermodal ecosystem where the entire container terminal and supporting infrastructure – including road, rail sidings, and future transload facilities – are all located on Port lands,” said Maksim Mihic, CEO and General Manager, DP World (Canada) Inc.  

“The opening of the new Fairview-Ridley Connector Corridor is great news for our economy and for the strength of our supply chains. The new Corridor will not only promote greater access to the Prince Rupert Gateway, but will also create good jobs for Canadians and enable further economic growth for the region,” said the Honourable Omar Alghabra, Minister of Transport.

Images and video from the opening can be found at rupertport.com/news


—30—

PROJECT TIMELINE:

  • Initially feasibility study was launched in 2011
  • CTNCA began early works to clear quarry sites in March 2018
  • Project received an investment of $15 million from the Asia-Pacific Gateway Initiative in late 2018
  • Early construction work began in May 2019
  • Project reached 20% completion in April 2020 with dredging and infill work continuing
  • Project reached 75% milestone in November 2020 with rock placed on full length of road
  • Rail sidings added in April 2022
  • Road paving completed in July 2022
  • Truck gate activation in August 2022

L-R: Shaun Stevenson, PRPA President & CEO; Hon. Harjit Sajjan, Minister of International Development; Chief Harold Leighton, Metlakatla First Nation; Sm’ooygit Gitxoon (Hereditary Chief Alex Campbell), Ricardo Alvarez, DP World Prince Rupert General Manager

See more news

News
April 8, 2024

Two New Directors Appointed to Prince Rupert Port Authority Board

The Prince Rupert Port Authority (PRPA) announced today changes to its Board of Directors.

Read More
News
March 7, 2024

Smithers Golf Course Hits a Hole-in-One With Upgrades Thanks to PRPA Partnership

The Smithers golf course is now up to par as a year-round recreational asset after work was done to make the course walkways accessible and safer throughout the winter months.

Read More
News
February 29, 2024

PRPA and Kitsumkalum Sign Relationship Agreement

The Prince Rupert Port Authority (PRPA) and the Kitsumkalum First Nation are pleased to announce that they have entered into a Relationship Agreement that will govern how the two organizations work together for years to come.

Read More